NCC 2025 Steel Framing: What NSW, ACT and Victorian Builders Need to Know

NCC 2025 steel framing rules already apply in Victoria, and they become the code in NSW and the ACT on 1 May 2027. If you are pricing jobs now that will be approved next year, the new edition affects you already.
This guide covers what changed for light gauge steel frames and trusses, what stayed the same, and what to check before your next frame order.
When Does NCC 2025 Apply in Each State?
| State | NCC 2025 start | What it means now |
|---|---|---|
| Victoria | 1 May 2026 | Applies to all new building work. Some provisions have a 12-month transition. |
| NSW | 1 May 2027 | NCC 2022 stays in force until then. |
| ACT | 1 May 2027 | Until then, approvals can use NCC 2022 or NCC 2025. Applications lodged before 1 November 2026 can keep either edition until the application expires. |
The NSW Government chose a 12-month transition to NCC 2025 so builders have time to adjust. The ACT is on the same timing. Ask your certifier which edition applies to your approval date before the frame design is locked in.
Building in Victoria or Canberra? See our steel frames Melbourne and steel frames Canberra pages.
No New Thermal Break Rules for Battened-Out Steel Framing
Early drafts of the energy efficiency provisions would have changed how thermal breaks are used in steel framed roofs and walls. NASH and BlueScope submitted testing and research, including work with the University of Wollongong, and the proposal did not go ahead.
The result: NCC 2025 adds no additional thermal break requirements for battened-out steel framing. If your current details use battens or thermal breaks to meet energy requirements, that approach carries over. Your energy assessor still needs to confirm total R-values for each wall and roof system.
Drained and Vented Cavities in Climate Zones 6, 7 and 8
NCC 2025 makes a drained and vented cavity mandatory for houses in cool and cold climates where lightweight cladding is fixed to timber or steel framing. The minimum cavity depth is 12 mm in Climate Zones 6, 7 and 8.
Canberra is Climate Zone 7 and Melbourne is Climate Zone 6 on the ABCB climate zone map. Coastal Sydney and Wollongong sit in Climate Zone 5, but zones change across NSW, so check the site address on the map every time.
Battening out the frame, or fitting thermal breaks, can reach the 12 mm depth without changing the frame itself. Before ordering, confirm:
- the climate zone for the site address
- the cladding type and its fixing method
- the batten or cavity depth on the wall details
- the wall wrap specified behind the cladding
Wall Wrap Permeance and Condensation
Minimum permeance requirements for control layers, such as wall wraps and pliable membranes, now apply in every climate zone. The Class 4 requirement for Climate Zones 6, 7 and 8 that came in with NCC 2022 is unchanged. Lower classes apply where condensation risk is lower.
These rules do not change the steel frame, but they do change the wall system around it. Get the wrap, cavity and insulation specified together so the frame layout, battens and openings line up on site.
Fire-Protected Steel Is Now a Deemed-to-Satisfy Option
For Class 2 to 9 buildings, NCC 2025 recognises fire-protected steel as a Deemed-to-Satisfy method for load-bearing internal walls. Before this, many commercial and mid-rise jobs needed project-specific fire engineering for the same wall.
The draft definition describes steel load-bearing walls lined with at least two layers of 13 mm fire-protective grade plasterboard on each side, plus any extra lining needed to reach the required FRL. That wording came from the draft preview, so check the final code text with your fire engineer or certifier.
This matters most for townhouses, apartments and top-floor additions. Read more on light gauge steel framing in top-floor construction and our structural steel work.
What Has Not Changed
- Steel frames and trusses are still designed to the NASH Standard. Our guide to lipped vs unlipped steel stud framing covers the profiles.
- Building ministers have agreed to pause further residential NCC changes until around 2029, apart from essential safety and quality fixes.
- The comparison with timber is the same as before. See timber vs steel frame Australia and the common problems with steel framed homes.
NCC 2025 Steel Framing Checklist for Your Next Job
- Confirm with your certifier which NCC edition applies to the approval.
- Look up the climate zone for the site address on the ABCB map.
- In Climate Zones 6, 7 and 8 with lightweight cladding, detail a drained and vented cavity of at least 12 mm.
- Check the wall wrap permeance class for that zone.
- For load-bearing internal walls in Class 2 to 9 buildings, ask about the fire-protected steel Deemed-to-Satisfy option.
- Send us final plans with cavity and batten details so the frames and trusses match what gets built.
Frequently Asked Questions
Q1. When does NCC 2025 start in NSW?
NCC 2025 is adopted in NSW on 1 May 2027. NCC 2022 stays in force until then.
Q2. Does NCC 2025 add thermal break requirements for steel frames?
No. There are no additional thermal break requirements for battened-out steel framing under NCC 2025.
Q3. Do I need a drained and vented cavity in Sydney?
It is mandatory for houses in Climate Zones 6, 7 and 8 with lightweight cladding. Coastal Sydney is Climate Zone 5, but other parts of NSW are in higher zones, so check the site address on the ABCB climate zone map.
Q4. Can I still use NCC 2022 in the ACT?
Until 1 May 2027, ACT approvals can use either NCC 2022 or NCC 2025. Development or works applications lodged before 1 November 2026 can keep using either edition until the application expires.
Planning a Job Under NCC 2025?
Send your plans and engineering to Steel Frames & Trusses and we will quote steel frames and trusses to suit your wall and roof details. Call 0473 00 00 66 or request a quote. Builders can also see our trade services.